Thank you for your question, Randy.

1) compute the Person Estimates and each of their S.E.s using the GPCM 
parameter estimates. Hopefully these are reported by the GPCM software.
2) square and average the person S.E.s = MSE = Error Variance
3) Person "Test" Reliability = True Variance / Observed Variance
= (Observed Variance - Error Variance) / Observed Variance = (Person 
S.D.**2 - MSE) / Person S.D.**2

OK?